Dubai Solar Project Planner (DEWA)

Lay out a whole rooftop project: roofs or zones, several inverter models, mixed string lengths on each inverter. Every string is checked against DEWA's DRRG rules and fitted to the inverter's MPPTs, and the project is checked against DEWA's capacity limit for the building's connected load.

Project

DEWA DRRG Standards 2.1: array voltage at 0 °C, 50 °C ambient. Panels and inverters on DEWA's eligible list are marked DEWA list.

DEWA capacity and energy

Monthly consumption from DEWA bills (kWh, optional)

How it checks

  • Voltage: Voc at the design minimum (0 °C by default) times panels per string, against the lowest of the inverter's max DC input, the panel's max system voltage and the DEWA voltage class.
  • Hot side: cell temperature from the PVsyst thermal model, Tcell = Tamb + 0.9 × 1000 × (1 − η) ÷ Uc, with Uc 20 (sheet roof), 25 (RCC roof) or 29 (carport). Vmp at that temperature must stay above the MPPT minimum.
  • MPPTs: one string length per MPPT, and no more strings on an MPPT than its inputs and short-circuit current allow.
  • String fuses: DRRG Standards 2.6.1, fuses when (strings in parallel − 1) × Isc is above the panel's max series fuse rating; gPV rating between 1.5 and 2.4 × Isc.
  • AC side: the inverter's max output current against DEWA's cable and breaker table.
  • Capacity: DEWA Connection Conditions 2.2, the share of the total connected load allowed per slab, up to 1,000 kW per plot.

Planning tool, not a DRRG submission. Check the datasheets, the DEWA standards in force and the eligible equipment list.

Planning a DEWA rooftop project step by step

1. Split the roof into zones

Group the roof areas by mounting type, because the cell temperature, and so the minimum string length, depends on it. A warehouse with a sheet roof and a concrete office block becomes two zones: sheet (Uc 20) and RCC (Uc 25). Carports are a third zone (Uc 29), and only carports that are not on a building can go above 1,000 V.

2. Pick inverters and a DC/AC ratio

For commercial rooftops in the UAE, a DC/AC ratio of about 1.15 to 1.3 is common. Higher ratios add energy in the morning and evening but clip more at noon, and Dubai's clear skies mean panels reach nameplate power more often than in cloudier climates. The planner's suggestion button finds a string split that hits your target without going over each inverter's maximum PV power.

3. Fit strings onto MPPTs

Each MPPT can carry only one string length, up to its number of inputs and its current rating. Mixed lengths are fine across MPPTs. On a 7-MPPT inverter with three inputs per MPPT, five strings of 15 and twelve strings of 17 use six MPPTs: two for the 15s (3 + 2) and four for the 17s. The planner shows this layout for every row and flags anything that does not fit.

4. Check DEWA's capacity limit

DEWA's Connection Conditions (section 2.2) limit the AC capacity by the building's total connected load (TCL) in slabs: 100% of the first 100 kW, 75% of the next 100 kW, 50% from 200 to 400 kW, 25% from 400 to 600 kW and 5% above that, up to 1,000 kW per plot.

Example: a TCL of 250 kW allows 100 + 75 + 25 = 200 kW of AC capacity. A TCL of 600 kW allows 100 + 75 + 100 + 50 = 325 kW.

5. Size the AC side

Each inverter's maximum AC output current sets its breaker and cable from DEWA's table. For example, the Sungrow SG150CX's 240.6 A needs a 250 A breaker on 150 mm² cable, and a Huawei SUN2000-100KTL-M2 (160.4 A) needs a 200 A breaker on 95 mm².

6. Estimate energy

Dubai rooftops typically produce about 1,700 to 1,760 kWh per kWp a year in PVsyst, depending on tilt, soiling and losses. Enter your own PVsyst figure for the best estimate, and your monthly DEWA bills to compare production with consumption. Under net metering, surplus energy is carried forward as a credit on the same premises rather than paid out.

Questions about planning a DEWA project

Can one inverter take strings of different lengths?

Yes, as long as each MPPT carries one string length. The planner fits your string groups onto the inverter's MPPTs, within each MPPT's inputs and current rating, and flags anything left over.

What DC/AC ratio is normal for Dubai rooftops?

Around 1.15 to 1.3 is common for commercial rooftops in the UAE. The planner can suggest a string split that hits your target exactly, without going over the inverter's maximum PV power.

How is the AC cable and breaker chosen?

From the inverter's maximum AC output current and DEWA's cable and breaker table (Regulations for Electrical Installations): for example 240.6 A needs a 250 A breaker on 150 mm² cable.

When does DEWA require string fuses?

DRRG Standards section 2.6.1: string overcurrent protection is needed when (number of parallel strings − 1) × the module short-circuit current is above the module's maximum series fuse rating. gPV fuses are then rated between 1.5 and 2.4 × Isc and no higher than the module's fuse rating.

How much solar can a building install under Shams Dubai?

DEWA's Connection Conditions (section 2.2) cap the AC capacity by the building's total connected load (TCL): 100% of the first 100 kW, 75% of the next 100 kW, 50% up to 400 kW, 25% up to 600 kW and 5% above that, up to 1,000 kW per plot. The Project Planner checks this for you.