Home › Gulf

Solar design tools for the Gulf

String sizing and project planning for the UAE, Saudi Arabia, Oman, Bahrain and Qatar, each set up for its own utility rules: design temperatures, DC voltage limit, string fuses, capacity and equipment approval. Free, in the browser, with the same datasheet library as the US tools.

Rules side by side

MarketScheme / rulesDesign temps (min / max)DC voltage limitCapacityEquipment
DubaiDEWA Shams Dubai (DRRG)0 °C / 50 °C1,000 V buildings, 600 V villas, 1,500 V canopiesTCL slabs, max 1 MW per plotDEWA eligible list (marked in the tools)
Abu DhabiDoE Self-Supply Policy (2026)0 °C / 50 °C (UAE practice)Not stated: equipment classNo fixed cap; self-supply, exports not nettedDistribution Code; confirm with ADDC / AADC
SharjahSEWA approval (no general scheme yet)0 °C / 50 °C (UAE practice)Not stated: equipment classWritten SEWA approval before energisingIEC + ECAS; confirm with SEWA
Northern EmiratesEtihad WE DSS Standards (2024)0 °C or lower / 50 °C1,500 V at 0 °C on buildings1 MW per premises; 10 kW per phase single-phaseEtihad WE approved list
Saudi ArabiaSEC small-scale PV standards; SERA framework−5 °C / 55 °C (SEC Annex D)Not stated: equipment class (1.5 kV cables)1 kW to 2 MW per premises; ≤ 11 kW single-phaseSASO conformity + Annex E standards
OmanSahim (APSR / Nama)0 °C / 50 °C (UAE practice)Not stated: equipment classNo published cap; exports paid at the Bulk Supply TariffConfirm with Nama
BahrainEWA net metering / net billing0 °C / 50 °C (conservative)Not stated: equipment classNet metering for homes ≤ 100 kW; net billing aboveEWA renewable equipment list (marked in the tools)
QatarKahramaa BeSolar0 °C / 50 °C (conservative)Not stated: equipment class (1.5 kV cables)≤ contracted demand, max 25 MW; 0.237 QAR/kWh exportKahramaa approved makers and series (marked in the tools)

Checked 26 Nov 2026. Where an authority publishes no value, the tools use UAE practice (0 °C and 50 °C) or IEC 62548 and say so on the page. Kuwait has no retail rooftop scheme yet.