Saudi Arabia Solar Project Planner (SEC / SERA)

Lay out a whole rooftop project: roofs or zones, several inverter models, mixed string lengths on each inverter. Every string is checked at Saudi Arabia's design temperatures and fitted to the inverter's MPPTs, and the project is checked against SEC / SERA's capacity rule.

Project

Saudi Arabia (SEC / SERA): array voltage at −5 °C, 55 °C ambient. Annex D of the SEC standards gives an outdoor ambient range of −5 °C to 55 °C, so the tool works out the string voltage at −5 °C and the hot-day voltage at 55 °C.

SEC / SERA capacity and energy

Default yield 1,850 kWh/kWp a year is a typical rooftop figure for Saudi Arabia; replace it with your PVsyst or PVGIS result.

Monthly consumption from SEC bills (kWh, optional)

How it checks

  • Voltage: Voc at the design minimum (−5 °C by default) times panels per string, against the lowest of the inverter's max DC input, the panel's max system voltage and the 1,000 V or 1,500 V class.
  • Hot side: cell temperature from the PVsyst thermal model, Tcell = Tamb + 0.9 × 1000 × (1 − η) ÷ Uc, with Uc 20 (sheet roof), 25 (RCC roof) or 29 (carport). Vmp at that temperature must stay above the MPPT minimum.
  • MPPTs: one string length per MPPT, and no more strings on an MPPT than its inputs and short-circuit current allow.
  • String fuses: IEC 62548, fuses when (strings in parallel − 1) × Isc is above the panel's max series fuse rating; gPV rating between 1.5 and 2.4 × Isc.
  • AC side: the inverter's max output current, to size the cable and breaker under IEC 60364-5-52 and SEC / SERA's wiring rules.
  • Capacity: Small-scale systems run from 1 kW to 2 MW per premises (section 4), within the Maximum Connected Capacity set under SERA's regulations (section 6.1). Single- and two-phase inverters are allowed only up to 11 kW (section 6.9.7.5).

Planning tool, not a utility submission. SEC keeps no equipment list. Panels and inverters need SASO conformity, and inverters must meet the standards in Annex E: IEC 62109-1/-2, IEC 62116, IEC TS 62910 and IEC 62920.

Planning a rooftop project in Saudi Arabia (SEC / SERA)

The physics is the same everywhere: Voc rises in the cold, Vmp falls in the heat, and each MPPT has current limits. What changes from market to market are the design temperatures, the voltage limit, the capacity rule and the equipment approval. This page applies SEC / SERA's rules where they are published, and IEC 62548 where they are not.

Design temperatures

Annex D of the SEC standards gives an outdoor ambient range of −5 °C to 55 °C, so the tool works out the string voltage at −5 °C and the hot-day voltage at 55 °C. Northern sites (Tabuk, Al-Jouf, Northern Borders) can get colder than −5 °C: use your site's record low there.

Voltage limit

SEC's Standards for the Connection of Small-Scale Solar PV Systems set no separate DC voltage limit; PV cables are specified for 1.5 kV DC (Annex E). Pick the 1,000 V or 1,500 V class that matches your panels and inverter; the tool also checks the inverter's maximum DC input and the panel's maximum system voltage.

For example, the Jinko Tiger Neo 3.0 JKM650N-66QL6-BDV has a Voc of 50.26 V and a coefficient of −0.24 %/°C. At −5 °C: 50.26 × [1 + 0.0024 × 30] = 53.88 V per panel, so up to 18 under a 1,000 V class and 27 under 1,500 V, if the inverter and panel are rated for it (20 on a common 1,100 V inverter). Pick your panel and inverter above for the exact answer.

Hot side and MPPT window

On the hottest day the cells run well above the air. The tool uses the PVsyst thermal model, Tcell = Tamb + 0.9 × 1000 × (1 − η) ÷ Uc, with Uc 20 for sheet roofs, 25 for concrete (RCC) roofs and 29 for carports, then checks that Vmp at that temperature stays above the inverter's MPPT minimum.

String fuses

Outside Dubai the tools use the IEC 62548 check, written the same way as DEWA's DRRG 2.6.1: string fuses are needed when (strings in parallel − 1) × the panel's short-circuit current is above its maximum series fuse rating. gPV fuses are then rated between 1.5 and 2.4 × Isc and no higher than the panel's fuse rating. Some editions add a safety factor to Isc, so near the limit check the edition your authority uses.

Capacity and scheme

Small-scale systems run from 1 kW to 2 MW per premises (section 4), within the Maximum Connected Capacity set under SERA's regulations (section 6.1). Single- and two-phase inverters are allowed only up to 11 kW (section 6.9.7.5).

Equipment approval

SEC keeps no equipment list. Panels and inverters need SASO conformity, and inverters must meet the standards in Annex E: IEC 62109-1/-2, IEC 62116, IEC TS 62910 and IEC 62920.

Sources

Rules checked 26 Nov 2026. These are planning tools, not a utility submission: always check the rules and lists in force before you apply.

Questions about planning a project in Saudi Arabia

Can one inverter take strings of different lengths?

Yes, as long as each MPPT carries one string length. The planner fits your string groups onto the inverter's MPPTs, within each MPPT's inputs and current rating, and flags anything left over.

What DC/AC ratio is normal for Gulf rooftops?

Around 1.15 to 1.3 is common for commercial rooftops in the Gulf. The planner can suggest a string split that hits your target exactly, without going over the inverter's maximum PV power.

How big can a solar system be in Saudi Arabia?

Small-scale systems run from 1 kW to 2 MW per premises (section 4), within the Maximum Connected Capacity set under SERA's regulations (section 6.1). Single- and two-phase inverters are allowed only up to 11 kW (section 6.9.7.5).

Which panels and inverters are approved in Saudi Arabia?

SEC keeps no equipment list. Panels and inverters need SASO conformity, and inverters must meet the standards in Annex E: IEC 62109-1/-2, IEC 62116, IEC TS 62910 and IEC 62920.