String sizing in Abu Dhabi (DoE / ADDC / AADC)
The physics is the same everywhere: Voc rises in the cold, Vmp falls in the heat, and each MPPT has current limits. What changes from market to market are the design temperatures, the voltage limit, the capacity rule and the equipment approval. This page applies DoE / ADDC / AADC's rules where they are published, and IEC 62548 where they are not.
Design temperatures
No design temperature is published in the self-supply policy. The tool uses 0 °C for the maximum string voltage and 50 °C ambient, the values DEWA and Etihad WE set for the UAE. Inland desert sites get colder than the coast, so lower the design minimum if your site has recorded sub-zero nights.
Voltage limit
The DoE Self-Supply Policy (Feb 2026) leaves technical limits to the Distribution Code and the DoE Solar PV Installation Guidance and states no DC voltage. Pick the 1,000 V or 1,500 V class that matches your panels and inverter; the tool also checks the inverter's maximum DC input and the panel's maximum system voltage.
For example, the Jinko Tiger Neo 3.0 JKM650N-66QL6-BDV has a Voc of 50.26 V and a coefficient of −0.24 %/°C. At 0 °C: 50.26 × [1 + 0.0024 × 25] = 53.28 V per panel, so up to 18 under a 1,000 V class and 28 under 1,500 V, if the inverter and panel are rated for it (20 on a common 1,100 V inverter). Pick your panel and inverter above for the exact answer.
Hot side and MPPT window
On the hottest day the cells run well above the air. The tool uses the PVsyst thermal model, Tcell = Tamb + 0.9 × 1000 × (1 − η) ÷ Uc, with Uc 20 for sheet roofs, 25 for concrete (RCC) roofs and 29 for carports, then checks that Vmp at that temperature stays above the inverter's MPPT minimum.
String fuses
Outside Dubai the tools use the IEC 62548 check, written the same way as DEWA's DRRG 2.6.1: string fuses are needed when (strings in parallel − 1) × the panel's short-circuit current is above its maximum series fuse rating. gPV fuses are then rated between 1.5 and 2.4 × Isc and no higher than the panel's fuse rating. Some editions add a safety factor to Isc, so near the limit check the edition your authority uses.
Capacity and scheme
Abu Dhabi's PV and Battery Energy Storage Systems for Self-Supply Policy (DoE, 5 Feb 2026) sets no fixed kW limit. Systems are for self-supply: exported energy is not netted or offset unless the DoE authorises it (section 2.1), so size the system to daytime load.
Equipment approval
Abu Dhabi has no public eligible-equipment list like DEWA's. Equipment must meet the Distribution Code and the DoE Solar PV Installation Guidance; confirm with your distribution company (ADDC or AADC) before you buy.
Sources
Rules checked 26 Nov 2026. These are planning tools, not a utility submission: always check the rules and lists in force before you apply.