Bahrain Solar Project Planner (EWA)

Lay out a whole rooftop project: roofs or zones, several inverter models, mixed string lengths on each inverter. Every string is checked at Bahrain's design temperatures and fitted to the inverter's MPPTs, and the project is checked against EWA's capacity rule.

Project

Bahrain (EWA): array voltage at 0 °C, 50 °C ambient. EWA publishes no design temperature online.

EWA capacity and energy

Default yield 1,700 kWh/kWp a year is a typical rooftop figure for Bahrain; replace it with your PVsyst or PVGIS result.

Monthly consumption from EWA bills (kWh, optional)

How it checks

  • Voltage: Voc at the design minimum (0 °C by default) times panels per string, against the lowest of the inverter's max DC input, the panel's max system voltage and the 1,000 V or 1,500 V class.
  • Hot side: cell temperature from the PVsyst thermal model, Tcell = Tamb + 0.9 × 1000 × (1 − η) ÷ Uc, with Uc 20 (sheet roof), 25 (RCC roof) or 29 (carport). Vmp at that temperature must stay above the MPPT minimum.
  • MPPTs: one string length per MPPT, and no more strings on an MPPT than its inputs and short-circuit current allow.
  • String fuses: IEC 62548, fuses when (strings in parallel − 1) × Isc is above the panel's max series fuse rating; gPV rating between 1.5 and 2.4 × Isc.
  • AC side: the inverter's max output current, to size the cable and breaker under IEC 60364-5-52 and EWA's wiring rules.
  • Capacity: Homes up to 100 kW are on net metering: surplus is carried forward to later months. Systems above 100 kW, and all non-residential systems, are on net billing: surplus is sold to EWA. Applications go through the Benayat portal.

Planning tool, not a utility submission. Panels and inverters must be on EWA's renewable equipment list, installed by an EWA-approved contractor and designed by an approved engineering office. The tools mark models on the list as EWA list (checked 26 Nov 2026).

Planning a rooftop project in Bahrain (EWA)

The physics is the same everywhere: Voc rises in the cold, Vmp falls in the heat, and each MPPT has current limits. What changes from market to market are the design temperatures, the voltage limit, the capacity rule and the equipment approval. This page applies EWA's rules where they are published, and IEC 62548 where they are not.

Design temperatures

EWA publishes no design temperature online. 0 °C is a conservative minimum for Bahrain, and equipment is checked at 50 °C ambient.

Voltage limit

EWA's online guidance doesn't state a DC voltage limit. Pick the 1,000 V or 1,500 V class that matches your panels and inverter; the tool also checks the inverter's maximum DC input and the panel's maximum system voltage.

For example, the Jinko Tiger Neo 3.0 JKM650N-66QL6-BDV has a Voc of 50.26 V and a coefficient of −0.24 %/°C. At 0 °C: 50.26 × [1 + 0.0024 × 25] = 53.28 V per panel, so up to 18 under a 1,000 V class and 28 under 1,500 V, if the inverter and panel are rated for it (20 on a common 1,100 V inverter). Pick your panel and inverter above for the exact answer.

Hot side and MPPT window

On the hottest day the cells run well above the air. The tool uses the PVsyst thermal model, Tcell = Tamb + 0.9 × 1000 × (1 − η) ÷ Uc, with Uc 20 for sheet roofs, 25 for concrete (RCC) roofs and 29 for carports, then checks that Vmp at that temperature stays above the inverter's MPPT minimum.

String fuses

Outside Dubai the tools use the IEC 62548 check, written the same way as DEWA's DRRG 2.6.1: string fuses are needed when (strings in parallel − 1) × the panel's short-circuit current is above its maximum series fuse rating. gPV fuses are then rated between 1.5 and 2.4 × Isc and no higher than the panel's fuse rating. Some editions add a safety factor to Isc, so near the limit check the edition your authority uses.

Capacity and scheme

Homes up to 100 kW are on net metering: surplus is carried forward to later months. Systems above 100 kW, and all non-residential systems, are on net billing: surplus is sold to EWA. Applications go through the Benayat portal.

Equipment approval

Panels and inverters must be on EWA's renewable equipment list, installed by an EWA-approved contractor and designed by an approved engineering office. The tools mark models on the list as EWA list (checked 26 Nov 2026).

Sources

Rules checked 26 Nov 2026. These are planning tools, not a utility submission: always check the rules and lists in force before you apply.

Questions about planning a project in Bahrain

Can one inverter take strings of different lengths?

Yes, as long as each MPPT carries one string length. The planner fits your string groups onto the inverter's MPPTs, within each MPPT's inputs and current rating, and flags anything left over.

What DC/AC ratio is normal for Gulf rooftops?

Around 1.15 to 1.3 is common for commercial rooftops in the Gulf. The planner can suggest a string split that hits your target exactly, without going over the inverter's maximum PV power.

How big can a solar system be in Bahrain?

Homes up to 100 kW are on net metering: surplus is carried forward to later months. Systems above 100 kW, and all non-residential systems, are on net billing: surplus is sold to EWA. Applications go through the Benayat portal.

Which panels and inverters are approved in Bahrain?

Panels and inverters must be on EWA's renewable equipment list, installed by an EWA-approved contractor and designed by an approved engineering office. The tools mark models on the list as EWA list (checked 26 Nov 2026).