String sizing in Northern Emirates (Etihad WE)
The physics is the same everywhere: Voc rises in the cold, Vmp falls in the heat, and each MPPT has current limits. What changes from market to market are the design temperatures, the voltage limit, the capacity rule and the equipment approval. This page applies Etihad WE's rules where they are published, and IEC 62548 where they are not.
Design temperatures
Section 2.1: work out the array voltage at 0 °C, or lower where the site gets colder (mountain sites such as Jebel Jais in Ras Al Khaimah). Inverters must cope with 50 °C, and with 60 °C at no more than 25% derating (sections 2.1 and 2.2.3).
Voltage limit
Etihad WE's Distributed Solar Systems Standards (section 2.1) limit rooftop systems to 1,500 V DC open-circuit at 0 °C. Above 1,500 V a system can't go on a building: only ground-mounted, canopy or restricted-access structures.
For example, the Jinko Tiger Neo 3.0 JKM650N-66QL6-BDV has a Voc of 50.26 V and a coefficient of −0.24 %/°C. At 0 °C: 50.26 × [1 + 0.0024 × 25] = 53.28 V per panel, so up to 28 under the 1,500 V rooftop limit, or 20 on a common 1,100 V inverter. Pick your panel and inverter above for the exact answer.
Hot side and MPPT window
On the hottest day the cells run well above the air. The tool uses the PVsyst thermal model, Tcell = Tamb + 0.9 × 1000 × (1 − η) ÷ Uc, with Uc 20 for sheet roofs, 25 for concrete (RCC) roofs and 29 for carports, then checks that Vmp at that temperature stays above the inverter's MPPT minimum.
String fuses
Outside Dubai the tools use the IEC 62548 check, written the same way as DEWA's DRRG 2.6.1: string fuses are needed when (strings in parallel − 1) × the panel's short-circuit current is above its maximum series fuse rating. gPV fuses are then rated between 1.5 and 2.4 × Isc and no higher than the panel's fuse rating. Some editions add a safety factor to Isc, so near the limit check the edition your authority uses.
Capacity and scheme
Up to 1 MW per premises (section 1), for Ajman, Umm Al Quwain, Ras Al Khaimah and Fujairah. Single-phase inverters are limited to 10 kW per phase, balanced across phases (section 2.5.1). Connection is at LV (240/415 V) or 11 kV.
Equipment approval
Main components must come from Etihad WE's List of Approved Equipment on its Solar Platform (section 2.1). Check it before you apply.
Sources
Rules checked 26 Nov 2026. These are planning tools, not a utility submission: always check the rules and lists in force before you apply.