Home › Gulf › Sharjah › String Sizer

Solar String Sizer for Sharjah (SEWA)

Panels per string for any panel and inverter under Sharjah (SEWA) rules: array voltage at 0 °C, 50 °C ambient, the 1,000 V or 1,500 V class, PVsyst cell temperature by roof type and the string fuse check. For a whole project with several inverters and roofs, use the Sharjah Project Planner.

Tera Labs
Solar string sizing report
Tera Labs · solar string sizing, compatibility and electrical calculators
teralabs.io · hello@teralabs.io

Sharjah (SEWA): string voltage worked out at 0 °C, equipment at 50 °C ambient. Hot-cell temperature uses the PVsyst model for the roof type you pick. String fuses follow IEC 62548.

Module checks

    String length options

    Voltage window

    MPPT range Full-power MPPT range Start-up voltage Max voltage

    Project calculator

    String diagram

    Prints this page as a 1–2 page report with the diagram.

    How this is calculated

      String sizing in Sharjah (SEWA)

      The physics is the same everywhere: Voc rises in the cold, Vmp falls in the heat, and each MPPT has current limits. What changes from market to market are the design temperatures, the voltage limit, the capacity rule and the equipment approval. This page applies SEWA's rules where they are published, and IEC 62548 where they are not.

      Design temperatures

      SEWA publishes no design temperature. The tool uses 0 °C for the maximum string voltage and 50 °C ambient, the values DEWA and Etihad WE set for the UAE.

      Voltage limit

      SEWA has not published a rooftop DC voltage limit. Pick the 1,000 V or 1,500 V class that matches your panels and inverter; the tool also checks the inverter's maximum DC input and the panel's maximum system voltage.

      For example, the Jinko Tiger Neo 3.0 JKM650N-66QL6-BDV has a Voc of 50.26 V and a coefficient of −0.24 %/°C. At 0 °C: 50.26 × [1 + 0.0024 × 25] = 53.28 V per panel, so up to 18 under a 1,000 V class and 28 under 1,500 V, if the inverter and panel are rated for it (20 on a common 1,100 V inverter). Pick your panel and inverter above for the exact answer.

      Hot side and MPPT window

      On the hottest day the cells run well above the air. The tool uses the PVsyst thermal model, Tcell = Tamb + 0.9 × 1000 × (1 − η) ÷ Uc, with Uc 20 for sheet roofs, 25 for concrete (RCC) roofs and 29 for carports, then checks that Vmp at that temperature stays above the inverter's MPPT minimum.

      String fuses

      Outside Dubai the tools use the IEC 62548 check, written the same way as DEWA's DRRG 2.6.1: string fuses are needed when (strings in parallel − 1) × the panel's short-circuit current is above its maximum series fuse rating. gPV fuses are then rated between 1.5 and 2.4 × Isc and no higher than the panel's fuse rating. Some editions add a safety factor to Isc, so near the limit check the edition your authority uses.

      Capacity and scheme

      SEWA had not opened a general rooftop net-metering scheme when we checked (November 2026). Any grid-tied system needs SEWA's written approval and a connection agreement before it is energised.

      Equipment approval

      Use IEC-certified equipment (IEC 61215 and 61730 panels, IEC 62109 and 62116 inverters) with ECAS conformity, and confirm acceptance with SEWA.

      Rules checked 26 Nov 2026. These are planning tools, not a utility submission: always check the rules and lists in force before you apply.

      Questions about string sizing in Sharjah

      What is the maximum DC voltage for rooftop solar in Sharjah?

      SEWA has not published a rooftop DC voltage limit. Pick the 1,000 V or 1,500 V class that matches your panels and inverter; the tool also checks the inverter's maximum DC input and the panel's maximum system voltage.

      What temperatures should I use for string sizing in Sharjah?

      SEWA publishes no design temperature. The tool uses 0 °C for the maximum string voltage and 50 °C ambient, the values DEWA and Etihad WE set for the UAE. On the hot side the tool uses the PVsyst thermal model with a loss factor (Uc) of 20 for sheet roofs, 25 for concrete (RCC) roofs and 29 for carports.

      How many solar panels can go in one string in Sharjah?

      For example, the Jinko Tiger Neo 3.0 JKM650N-66QL6-BDV has a Voc of 50.26 V and a coefficient of −0.24 %/°C. At 0 °C: 50.26 × [1 + 0.0024 × 25] = 53.28 V per panel, so up to 18 under a 1,000 V class and 28 under 1,500 V, if the inverter and panel are rated for it (20 on a common 1,100 V inverter). Pick your panel and inverter above for the exact answer.

      When are string fuses needed?

      Outside Dubai the tools use the IEC 62548 check, written the same way as DEWA's DRRG 2.6.1: string fuses are needed when (strings in parallel − 1) × the panel's short-circuit current is above its maximum series fuse rating. gPV fuses are then rated between 1.5 and 2.4 × Isc and no higher than the panel's fuse rating. Some editions add a safety factor to Isc, so near the limit check the edition your authority uses.

      How big can a solar system be in Sharjah?

      SEWA had not opened a general rooftop net-metering scheme when we checked (November 2026). Any grid-tied system needs SEWA's written approval and a connection agreement before it is energised.

      Which panels and inverters are approved in Sharjah?

      Use IEC-certified equipment (IEC 61215 and 61730 panels, IEC 62109 and 62116 inverters) with ECAS conformity, and confirm acceptance with SEWA.