PV wiring has its own sizing rules because solar current behaves differently from household loads: it runs at full output for hours, and on a bright, cool day with reflection from clouds it can exceed the panel's rated short-circuit current. NEC 690.8 handles this with two 125% factors.
Step 1: the circuit's maximum current
For a PV source circuit (a string), the maximum current is the panels' short-circuit current times 125%, which covers irradiance above the 1000 W/m² test level (NEC 690.8(A)):
(Qcells Q.TRON BLK M-G2+ 430, Isc 13.74 A.) For strings in parallel, add the strings' Isc together before applying the factor.
Step 2: the conductor's minimum ampacity
Because PV current is continuous, conductors and overcurrent devices must be rated for 125% of that maximum current (NEC 690.8(B)). The two factors together give the well-known 156% rule:
A 10 AWG copper conductor comfortably covers this in most conditions, which is why 10 AWG PV wire is the default for residential strings.
Step 3: correct for heat and conduit
A conductor's listed ampacity assumes a 30 °C ambient. Rooftop runs are hotter, and several current-carrying conductors in one conduit heat each other. Apply the temperature correction and conduit fill adjustment factors from NEC 310.15 to the conductor's ampacity, and confirm the corrected ampacity still covers I_max (17.2 A here). This check uses I_max, not the 156% figure, and the larger of the two results decides the wire size. Keep conduit off the roof surface where you can, because conduit close to the roof runs especially hot.
Step 4: voltage drop
The NEC does not set a maximum voltage drop for PV circuits, but lost voltage is lost energy, so designers commonly aim for 2% or less on the DC side. For a two-wire DC run:
An 11-panel string runs at about 362 V and 13.05 A. Over a 100 ft one-way run of 10 AWG copper (about 1.24 Ω per 1,000 ft):
High string voltage is the reason DC voltage drop is rarely a problem on string systems. It matters more on low-voltage battery circuits and long AC runs to a detached building, where heavier wire may be needed.
Step 5: do the strings need fuses?
When strings are connected in parallel, a fault in one string can be fed by all the others. If that backfeed can exceed the panel's maximum series fuse rating, each string needs a fuse (NEC 690.9):
- Two strings: 17.2 A, below this panel's 25 A rating, so no fuses.
- Three strings: 34.4 A, above 25 A, so fuse each string. The fuse must be at least 156% of Isc (21.5 A, so a 25 A fuse) and no larger than the module's series fuse rating.
Checklist
- Use the 156% rule for the conductor and the fuse.
- Correct for rooftop temperature and conduit fill.
- Aim for about 2% voltage drop or less on DC runs.
- Fuse strings when three or more are in parallel.
- Use conductors rated for sunlight and wet locations (PV wire or USE-2) where they are exposed.